Project Highlights

  • Location : Ambatolampy; Madagascar
  • Capacity : 20 MW
  • Timeline : Aug 2022 – April 2023
    Comprehensive EPC Services Provided
  • Engineering Design Review
  • Civil Works
  • Assembly and installation of 22/63 KV. Substation Apparatus and Equipment.
  • Electrical Equipment Installation
  • Project DC; LV AC and MV Works
  • 63 KV Overhead Line Works
  • Plant Testing; Cold and Hot Commissioning
  • Redlining of Engineering Design Drawings